Welcome and International Context
LBNF/DUNE Introduction and LBNF Management
DUNE Management and Project Status
LBNF/DUNE Cost/Schedule/Risk Update & LBNF Status Update - no video
LBNF/DUNE Cost/Schedule/Risk Update & LBNF Status Update - with video
Break
CD-3a Scope - Changes and Status
Lunch
Subcommittee Breakout Sessions
DOE Full Committee Executive Session
DOE Subcommittee Session
Adjourn
Parallel Subcommittee Breakout Sessions
Answers to Reviewer Questions
Working Lunch
DOE Full Committee Executive Session/Report Writing
DOE Full Committee Executive Session/Dry Run
Closeout
Cost/Schedule Re-estimate Process
Risk Management
Project Cost/Schedule and Contingency Status
Procurement Status
LBNF Management Update and International Planning
Estimates and BOEs
Formal EVMS before CD-2
SDSTA ESH for LBNF/DUNE Activities
Radiation Safety Update
Beamline Overview
Beamline Plan to CD-2
Primary Beam Status
Neutrino Beam Status
Beamline Risks
Tritium Mitigation Plan
International Contributions
FSCF Construction Management Update
Reliability Projects Status
ProtoDUNE Results & Lessons Learned
DUNE Collaboration Plans for TDR and CDR
U.S. APA
U.S. Cold Electronics
Report from the LBNC
QA for FSCF Construction
ESH for FSCF Construction
EXC Design Status
BSI Design Status
FSCF Procurement Update
FSCF Cost/Schedule/Risk Status
NSCF Design and Cost/Schedule/Risk Status
NSCF Procurement Update
QA for NSCF
ESH for NSCF
DUNE-US Project Overview
Technical Coordination
Systems Engineering & Configuration Management
Far Site Logistics Planning
Host Lab Planning at SURF
Final Discussion
Return to Plenary Agenda
Cryogenic Infrastructure Scope, Schedule & DOE Cost
Cryostat Status Update
Nitrogen Refrigeration System Status Technical Summary / Nitrogen Refrigeration System Procurement Status
Proximity Cryogenics in CUC
Proximity Cryogenics in Detector Cavern
Process Controls Update
Cryogenics ESH Update
LAr Supply
Receiving Facilities
Internal Cryogenics
Cryogenics Infrastructure Plan to CD-2
Return to Plenary Agenda
Reviewer photo
LBNF DOE Review Recommendations
DUNE-US DOE Review Recommendations
Bus from WH Horseshoe to IARC for Directorate and Review Committee
Bus from IARC to WH Horseshoe for Directorate and Review Committee
Femilab ESH Support for LBNF/DUNE Activities
QA for FSCF Construction (CF Breakout)
ESH for FSCF Construction (CF Breakout)
Approach to Project-wide ESH
Approach to Project-wide QC/QA
Cryogenics ESH Update (Cryo breakout)
QA for NSCF (CF breakout)
ESH for NSCF (CF breakout)
Discussion on Amplified Risk
Discussion
Discussion on Assumptions and Quasi-RAM for Contributions
Drilldowns?