Agenda


  
Content
  
collapse Date (Calculated) : 6/22/2018 ‎(8)
08:00

​Introductions

08:10

​Big Picture - How to get to Option 1A Award to Start Ross Shaft

  1. Scope of conveyor and Ross Shaft completion tasks defined by FRA
  2. FRA to define spill collection system change, clarification of skip loading system, and ore pass resolution
  3. Need KAJV schedule agreed upon by FRA
  4. FRA needs as much cost certainty as possible
  5. Need agreed upon CM/GC services cost
Doug Pelletier
08:30

​Work Task Allocation – who does what?

  1. See "Ross Shaft Completion Tasks, Revision 4, June 18, 2018"
Tracy Lundin
11:00

See “Proposed Time Phased Access Rules, Revision 1, June 18, 2018”

Tracy Lundin
12:00

Lunch

13:00

​Constraints, Barriers, and Decisions Required

  1. Schedule constraints for use of the Yates Shaft – only 4 days/week
  2. Verify with Tiley that simplified spill collection system approach is a go
  3. Interfaces with Reliability projects
  4. Procurement concerns/issues
Josh Willhite
14:00

Discuss Schedule

Josh Willhite
16:00

Adjourn