 6/22/2018 8:10 AM08:106/22/2018Doug Pelletier

​Big Picture - How to get to Option 1A Award to Start Ross Shaft

  1. Scope of conveyor and Ross Shaft completion tasks defined by FRA
  2. FRA to define spill collection system change, clarification of skip loading system, and ore pass resolution
  3. Need KAJV schedule agreed upon by FRA
  4. FRA needs as much cost certainty as possible
  5. Need agreed upon CM/GC services cost
6/22/2018
 6/22/2018 8:30 AM08:306/22/2018Tracy Lundin

​Work Task Allocation – who does what?

  1. See "Ross Shaft Completion Tasks, Revision 4, June 18, 2018"
6/22/2018
 6/22/2018 11:00 AM11:006/22/2018Tracy Lundin

See “Proposed Time Phased Access Rules, Revision 1, June 18, 2018”

6/22/2018
 6/22/2018 12:00 PM12:006/22/2018

Lunch

6/22/2018
 6/22/2018 1:00 PM13:006/22/2018Josh Willhite

​Constraints, Barriers, and Decisions Required

  1. Schedule constraints for use of the Yates Shaft – only 4 days/week
  2. Verify with Tiley that simplified spill collection system approach is a go
  3. Interfaces with Reliability projects
  4. Procurement concerns/issues
6/22/2018
 6/22/2018 2:00 PM14:006/22/2018Josh Willhite

Discuss Schedule

6/22/2018
 6/22/2018 4:00 PM16:006/22/2018

Adjourn