Deliverable
Develop a Risk Management Plan
Comply with the One-for-One Building Space Replacement
Complete a Conceptual Design Report
Document High Performance & Sustainable Building & Sustainable Environmental Stewardship Considerations
Prepare a Preliminary Hazard Analysis Report
Develop and Implement an Integrated Safety Management Plan
Establish Preliminary Quality Assurance Program (QAP)
Identify general Safeguards and Security requirements for the recommended alternative
Complete National Environmental Policy Act (NEPA) Strategy by issuing a determination
DOE Acquisition Strategy
DOE Preliminary Project Execution Plan
Integrated Project Team
Conceptual Level Cost and Schedule
Conduct a Conceptual Design Review