Requirement
Deliverable

​Update DOE Preliminary Project Execution Plan

​Complete Final Design

  • Incorporate High Performance & Sustainable Building & Sustainable Environmental Stewardship
  • Conduct Final Design Review
  • Complete Final Design Report

​Establish a Performance Baseline (for CD3a Scope)

​Employ a Certified EVMS Compliant with ANSI/EIA 748

​Prepare and Update the Hazard Analysis Report

​Prepare Construction Project Safety and Health Plan

​Update the Quality Assurance Program

​Issue Final NEPA Determination

​Finalize the Security Vulnerability Assessment Report