Question
Answer
Category
  
  
  
What is the current working number for the CD3A EAC?

Was the pending change of $34M included in the EAC in the September report?
Cost and Schedule10/23/2018
  

Identify ​the necessary s​teps between now and Jan IPR ​

Management10/26/2018
  

​Provide a comparison of the recommended labor escalation factors with the actual increases in SWF for fiscal years 16, 17 and 18.

Cost and Schedule10/26/2018
  

​Show us the cost impact on NS and FS CF base costs and EU contingency using escalation at 4% in place of the current 3.4% ​

Cost and Schedule10/26/2018
  

​Provide a crisp CD phasing strategy starting with partners in 2019, and include pros/cons for phasing​

Management10/26/2018
  

​One slide version on A/E and CMGC cost differences, what happened, future prospects

Cost and Schedule10/26/2018
  
Provide a table, by control account, identifying the value of budget based on bids in-hand vs. estimates.
10/26/2018
  
How much scope by $ value would the BCP move out of CD-3a?
Cost and Schedule10/26/2018