Agenda

 

1.  Risk changes and status 

Retired: 

PM-021 NEPA Approval is Delayed

PM-104  US-CERN Neutrino Protocol is Delayed

2.   Overall  DOE TPC changes

a. Elaine will show a table

b. Change Control database is tracking changes since CD1R - review 4 new scope options and changes that affect LBNF/DUNE

​SCOPE OPTIONS:
​CR0019  Add Office space at SURF
​CR0024  Add ​Cell Phone Leaky Feeder
​CR0030 Add redundant fiber in Yates Shaft
​CR0033 Add early ventilation improvements - 17 ledge

c. possible items to move to scope options:

​INCREASE IN SURFACE ROSS SUBSTATION CAPACITY FOR 4TH CRYOSTAT FILLING
​HEADFRAME REPAIRS
​PARKING LOT REPAIRS

       

 

  
  
  
  
  