1. Discuss document release dates

2. Director's review dry run schedules:

  • Plenary scheduled Friday 22 May all day - will include Fermilab Chief Project Officer participation
  • Management parallels planned for Tuesday 26 May, maybe in pieces (have Fermilab POG meeting interference 9-11 CT). Elaine/Eric will create a schedule. Please provide windows of opportunity.
  • Please let Elaine & Eric know about other parallel session dry run plans.

3.  CD-1 DOE Review scheduled for 7-9 July per recent draft charge we've reviewed.

4.  Powerpoint talk templates available - will customize for CD1R director's review in next week.

     LBNF:  http://lbne2-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=10894 

     DUNE: http://lbne2-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=10895

5.  Cost/schedule information - see JMT documents at right


 

  
  
  
  
  
LBNF-DUNE OblProfile for DOEscope-20150511 - What Ifwith lower contingency.xlsx
  
5/11/2015 7:48 PMElaine G MccluskeyMay 12, 2015
LBNF-DUNE summary schedule-20150511.pdf
  
5/11/2015 7:49 PMElaine G MccluskeyMay 12, 2015
LBNF-DUNE summary schedule-alt1-20150511.pdf
  
5/11/2015 7:49 PMElaine G MccluskeyMay 12, 2015
  
  
  
  
There are no items to show in this view of the "JMT Action Items" list.